- Home
- About TVF&R
- Funding
- Capital Construction Projects
- Relocate Logistics Service Center
Relocate Logistics Service Center
What Prompted the Need to Relocate?
TVF&R’s Logistics Services were housed at the North Operating Center in Aloha. Originally built in 1979, this campus was recently sold to Washington County. District leaders recognized the need to centrally locate these services within our boundaries to better serve the entire District.
Project Highlights
Acquisition
TVF&R’s original plan was to build a new facility. However, the opportunity to purchase and retrofit an existing facility allowed for potential cost and time savings. The 40,000-square-foot building is located on 4.5 acres at 9991 SW Avery St. in Tualatin.
Logistics Service Functions
The District’s logistics service functions based at this facility will include: supply warehouse, fleet maintenance, communications, facilities maintenance, and administrative staff.
Building Features
The Logistics Service Center will be built to essential facility standards. Essential facilities are buildings that support functions necessary for post-earthquake response and recovery. These facilities typically include police stations, fire stations, 911 dispatch centers, hospitals, schools, power-generating facilities, etc.
The building will feature seismic upgrades that meet current codes to withstand a major earthquake. In addition to staff workspaces, the building will have a meeting room, common work and storage areas, break rooms, and a workout room. It will be designed to operate for a minimum of 30 years.
Project Update
November 2020
Construction is nearing completion. The Logistics Service Center sign and flag poles are in place. The loading dock area and fitting rooms for apparel are complete. Oil tanks are installed in the fluids room, and the accent color has been painted on walls in the kitchen. Shelving racks are being seismically anchored.
October 2020
Construction is nearing completion, and move-in is anticipated to in mid-December. The fleet bay entrance doors are painted, storefront systems are installed, locker room showers and tile work are complete, and backboard washing equipment is set. Shelving is installed in the supply warehouse, and the vehicle exhaust system (pictured below) is complete in the fleet bays. Specialty workshop areas are also set up in the building.
September 2020
Interior finish work and site work continue. Patio and entryway are prepped for concrete. Casework and lockers are installed. Rooftop equipment is in place. Recent wildfires impacted site operations and individual construction crews.
August 2020
Installation of interior lighting and site work continue. The contractor polished concrete floors, placed steel frames for the truck wash, installed the ceiling grid and lights in the office space, and set compressed air outlets in the workshop. Fleet bay crane system installation began.
July 2020
Interior painting is ongoing. The contractor completed painting the walls in the supply warehouse and began installation of the fleet bay crane and ceiling grid. Site work continues. The generator was installed, and concrete was poured for the truck wash area.
June 2020
Drywall and exterior site work continues. The contractor completed the installation of HVAC units on the roof. Mezzanine installations are nearing completion, and interior door and window frames are in place.
May 2020
Drywall work is ongoing. The contractor continues interior mechanical, electrical, and plumbing work as well as exterior site work. Rebar and concrete work are being set for the loading dock. Insulation was placed in the fleet apparatus bays. Mezzanines are being installed for the supply warehouse, and trenching for site utilities began.
April 2020
The city issued Phase 2 permits. The contractor cleared trees from the site, and the electrical, plumbing, and HVAC rough-in work is nearly complete.
March 2020
The city is ready to issue Phase 2 permits. Meanwhile, the contractor continues electrical, plumbing, and HVAC work and began preparations for mezzanine footings.
February 2020
Electrical and plumbing work continues and framing is nearing completion at the station. The city continues to review the Phase 2 permit submittals.
January 2020
The contractor continues framing work and began electrical and plumbing work in the building.
December 2019
The contractor began framing and interior work.
November 2019
Phase 1 work is complete, including creation of exterior openings, new roof installation, seismic upgrades, and addition of a new fleet truck concrete bay. The capital projects team waits for the city to finish its review of Phase 2 permit requests.
October 2019
The city continues to review the Phase 2 permit submittals. Meanwhile, contractors poured the depressed slab for the fluids room and cut additional exterior openings in the building in preparation for Phase 2 work to begin.
September 2019
The capital projects team submitted Phase 2 permitting documents to the city of Tualatin. Contractors prepared the fleet apparatus bays for concrete and are placing sheet metal flashing on the roof of the building.
August 2019
The capital projects team is working to complete Phase 2 design documents. Meanwhile, contractors are nearly finished with roof work and started underground plumbing work.
July 2019
Contractors cut a new opening for the fleet bays into the building, began interior concrete demolition, and continue roof work.
June 2019
The capital projects team continues to work through the architectural review process for the remaining project scope. Meanwhile, the first phase of demolition work began. All existing shelving was dismantled and stored off-site.
May 2019
The capital projects team submitted permit applications to complete early seismic work. The seismic package plans are under review by city staff. The design team plans to submit additional items to the city for architectural review.
April 2019
The capital projects team submitted an architectural review package to the city.
March 2019
Design work continues.
February 2019
The capital projects team continues design work for renovating the existing facility.