An artist's rendering shows what the proposed station remodel will look like from the outside.
February 2016
Sub-contractor bid documents have been issued. Depending on permit approval dates, the contractor now plans to begin construction in April with a target completion of the project in July or August 2017.
January 2016
The plans and project specifications have been submitted for permit. The project team continues its work on bid documents. The contractor plans to mobilize in March, pending permit approval.
December 2015
Plans are 90 percent complete. The Board of Directors approved a lease agreement with Sunset Covenant Church to place a temporary station and apparatus shelter at 18555 N.W. Rock Creek Blvd. Crews are expected to move to the temporary site in late February 2016. They will provide service from the temporary location while the existing station is seismically upgraded.
November 2015
The team is working on bid documents. The construction manager/general contractor guaranteed maximum price will be presented to the Board of Directors for approval at the December board meeting. District staff members are working on an agreement with Sunset Covenant Church to lease vacant land at 18555 N.W. Rock Creek Blvd. to site a temporary fire station to allow the crew to continue to provide emergency response services in the area while the existing station is under construction. The church property is 1/10 of a mile away from Station 64.
October 2015
The project team submitted plans and specifications for permits.
September 2015
The project team continues to work on developing construction documents for Station 64. The plans and specifications are 80 percent complete. District staff members are negotiating for the use of a property to site a temporary station while the existing building is improved.
August 2015
District staff members are in discussions with property owners for the use their site for establishing temporary housing for firefighters while Station 64 is being improved. The project team continues to work through design development plans.
July 2015
The project team has completed 60 percent of the design development phase of the project. The seismic upgrades and remodel of the station are expected to be completed in spring 2017.
June 2015
A land-use application for Station 64 has been submitted. The project team continued to work through the design development phase of seismic upgrades and the station remodel.
May 2015
The project team continued to work through the design development phase of seismic upgrades and the station remodel.
The target completion date is in spring 2017.
April 2015
With approval of the schematic designs, a project team has moved into the design development phase of seismic upgrades and the remodel of Station 64.
March 2015
A project team has started to prepare for design development of seismic upgrades and the remodel of Station 64. The project is expected to be completed in spring 2017. This is one of three District projects that have received awards from the Seismic Rehabilitation Grant Program.