FacebookTwitterYouTube

Go To Search
I'm Looking For...

Rivergrove Station 39 - New Station
Click HERE to subscribe to construction updates.

Location/Service Area
Station 39 is located on a 1.16-acre site at 7100 SW McEwan Road in Tualatin. The future station's service area includes single- and multi-family housing as well as industrial and commercial structures.

Why a New Station?
Fire District leadership conducted a thorough analysis of population density, incident types, and traffic when determining the ideal location for the new station. TVF&R identified the need for a station in this location to ensure fast and effective emergency response to local residents and businesses and to strengthen emergency response in the Rivergrove community and nearby Bridgeport Village area.

Project Description
Rivergrove Station 39 will be a single-story fire station staffed around the clock by a four-person crew with room to expand if call volume increases. The station will feature a community meeting room.

Estimated Construction Timeline
Construction is tentatively scheduled to begin in summer 2018 with a target completion of summer 2019.

Station 39 rendering

7100 SW McEwan Road
Tualatin, OR 97062


Project Update

May 2018
Design development work continues.

April 2018
The conditional-use public hearing was held earlier this month, and no opposition was submitted. The capital projects team continues design development work.

March 2018
The capital projects team continues work in the design development phase. The conditional-use application is under review by city staff.

February 2018
The Tualatin City Council is scheduled to hold a public hearing on April 9 to consider the conditional-use application. Meanwhile, the capital projects team is working on the construction document. 

January 2018
The conditional-use application is complete, and the city of Tualatin scheduled a conditional-use hearing for April 9. If approved, the capital projects team has a target date of mid-April to submit the application for architectural review.

December 2017
The design development phase continues. The capital projects team submitted the conditional-use application to the city of Tualatin on December 8.

November 2017
The station schematic design is complete, and the capital projects team is moving into the design development phase. A neighborhood meeting for the land-use application was held on November 7. The team plans to submit a conditional-use application to the city of Tualatin by December 13.