Rosemont Station 55 - New Station
20790 Hidden Springs Road
West Linn, OR 97068


Project Status: COMPLETED

Open House Set
The community is invited to attend a Station 55 Open House from 11 a.m. to 2 p.m. on Saturday, October 6. A brief ceremony will be held at 11:30 a.m. Please join us for this free, family-friendly event. Guests can tour the new fire station, meet firefighters who operate out of the station, learn fire and life safety tips, and take a quick lesson in hands-only CPR.
Parking is available at Trillium Creek Primary School, 1025 SW Rosemont Road, where we will provide shuttle service to and from the station.

Your levy investment made construction of this new station possible and strengthened our emergency response system. TVF&R is grateful for your support while Station 55 was being constructed. We look forward to seeing you at the event. For more information, call 503-259-1500.

Station 55 Open House Invitation

Click HERE to subscribe to station updates.

Location/Service Area
Station 55 is located on a 2.6-acre site along Hidden Springs Road near Rosemont. It shares a southern boundary with Trillium Creek Primary School. The new station’s service area includes single- and multi-family housing, commercial structures, and areas of forest and agricultural land.

Why a New Station?
Fire District leadership conducted a thorough analysis of population density, incident types, and traffic when determining the ideal location for the new station. TVF&R identified the need for a station in this location to ensure fast and effective emergency response to local residents and to strengthen emergency response in the greater West Linn area. Due to the topography of the area and transportation network in West Linn, locating the station at the top of the hill at this location offers the best coverage and fastest response times to emergency incidents.

Project Description
Rosemont Station 55 is a single-story fire station staffed around the clock by a four-person crew with room to expand if call volume increases. The station features a community meeting room, which will be available for the public to reserve beginning September 15.

Exterior of Station 55

Project Update

August 2018
The crew moved into their new quarters on August 20. Firefighters are now operating out of Station 55 and responding to incidents.
Crew on move-in day
Firefighters began responding to emergency incidents out of Station 55 on August 20.

July 2018
The station is steadily nearing completion as contractors continue final punch list work.
Station 55 Landscape WorkStation 55 Tiller Drive Through
Landscape work is nearly complete. The tiller truck drove through the apparatus bay in preparation for move-in. Meanwhile, contractors installed office furniture as well as cabinets in the shop.
Station 55 Office FurnitureShop Cabinets in Station 55

June 2018
Contractors completed all concrete work on the site. Half-street improvements required by the city are nearly complete.
Station 55 Bay DoorsStation 55 concrete work
Apparatus bay doors are installed, and the final concrete pour at the station is complete. Inside the station, the EMS sink is in place, and appliances are being installed.
EMS sink in Station 55Appliances in Station 55 kitchen

May 2018
Installation of interior finishes is ongoing, and exterior site work continues. Contractors are nearly finished with installation of mechanical systems.
Station 55 siding work in MayMay concrete work
Siding installation is nearly complete. Contractors poured concrete for sidewalks; completed the epoxy floors in the locker rooms, public restrooms and utility closet; and installed interior casework in the kitchen, locker rooms, laundry room and community room.
epoxy floors in station
interior casework in station

April 2018
Contractors completed drywall installation. Roof work is nearing completion, and installation of exterior finishes continues.
Roof Work Station 55Siding Installation Station 55
Contractors installed shingles on the roof and begin installing siding. Below, preparation for the sidewalk begins, and contractors install the ceiling grid in the station's exercise room.
Station 55 Sidewalk PreparationStation 55 Exercise Room Ceiling Work

March 2018
Contractors continue to move forward with roofing and drywall installation. Meanwhile, painting and installation of exterior finishes begins on the new station.
Station 55 Roof Work in MarchStone veneer installation begins on exterior of Station 55.
Roof work continues and contractors begin the installation of stone veneer on the exterior of the station. Below, the heat pumps are placed, and drywall installation continues.
Drywall is installed inside Station 55.Heat pumps installed at Station 55

February 2018
Contractors completed framing work on the building and began installing interior insulation and drywall. Mechanical, electrical and plumbing rough-in work continues.
55Feb1.jpg55Feb2.jpg
Contractors began installing windows. Roofing work and building wrap installation is ongoing. Drywall was installed in the future community room, and shower installation started.
55Feb4.jpg55Feb3a.png

January 2018
Contractors began wrapping the building and installing the roof. Meanwhile, framing continues along with mechanical, electrical and plumbing rough-in work.
55Jana.jpg55Janb.jpg
Building wrap and roof installation is ongoing. Below, electrical and plumbing rough-in work continues. Contractors installed the air ducts in the station's future community room.
55Janc.jpg55Jand.png

December 2017
Site work continues. Contractors installed roof trusses and continue to frame the future station.
55Deca.jpg55Decc.jpg
Framing work is ongoing. Contractors installed the roof trusses, and the concrete block enclosures for the future generator and propane tank are complete.
55Decd.jpg

November 2017
Site utility work continues. Building construction is underway. Contractors poured the slab and started framing.
55Novembera.jpg55Novemberb.jpg
Framing materials are stocked for the work in progress. Contractors have placed the stem walls on footings for the station's garden shed, below.
55Novemberc.jpg

October 2017
The project is moving along. Contractors continue concrete work and prepare for framing to begin.
55October.jpg
The concrete slab takes shape.

September 2017
Contractors are keeping busy on the site with excavation and concrete work and importing fill for site subgrade.
55 Septa.jpg55 Septb.jpg
Contractors poured the footings and continue work beneath the wall. A vehicle barrier has been installed.
55 Septc.jpg

August 2017
Site work continues. Contractors are installing electrical and plumbing utility infrastructure. Excavation for building footings is complete. Formwork and pours are scheduled.
55-Augusta.jpg55-Augustb.jpg
The retaining wall is complete. Contractors work on fine grading for the main portion of the building pad. Below, plumbing and electrical infrastructure is installed.
55-Augustc.jpg

July 2017
Contractors are importing fill for site sub-grade and concrete work. Excavation and other site work continues.
55julya.jpg55julyb.jpg
Contractors import fill, build a retaining wall and form footings.
55julyc.jpg

June 2017
Contractors began installation of a mechanically stabilized retaining wall.
55Junea.jpg55Juneb.jpg
Construction is underway, and we would like to thank our neighbors for the donation of a picnic table for our contractors to use on site.
55Junec.jpg

May 2017

The project team has received site permits from the city, and the contractor has started mobilization activities.
May55a.jpgMay55b.jpg
Contractors prepared a portion of the site for a job shack that was delivered and placed.

February 2017
The architect and engineering team submitted plans to the city of West Linn for permit review and approval.

January 2017
The city approved the conditional land-use application, and the appeal period closed. The architect continued to develop plans, and the project team completed the quality assurance review.

December 2016
The city of West Linn held a land-use hearing on December 7. The project team continued to work on the development of plans and specifications for the station.

October 2016
The city deemed the land-use application for Station 55 complete.

September 2016
The project team submitted the land-use application to the city of West Linn on September 13.

June 2016
The project team continued to work through the land-use application approval process. The team attended the Hidden Springs Neighborhood Association meeting on June 21.

May 2016
TVF&R purchased property from the West Linn-Wilsonville School District. A schematic design of the station was completed, and a pre-application conference with the city was held on May 19.

April 2016
Due-diligence work was completed. The district expected to close on property acquisition within the next few weeks.